Primer Application:
Gallons Needed: 1,560 sq ft / 250 sq ft per gallon = 6.24 gallons (round to 7 gallons)
Material Cost: 7 gallons x $30/gallon = $210
Labor Hours: 1,560 sq ft / 1,000 sq ft per hour = 1.56 hours
Labor Cost: 1.56 hours x $25/hour = $39
Total Primer Cost: $210 (material) + $39 (labor) = $249
Stucco Application:
Gallons Needed: 1,560 sq ft / 50 sq ft per gallon = 31.2 gallons (round to 32 gallons)
Material Cost: 32 gallons x $30/gallon = $960
Labor Hours: 1,560 sq ft / 400 sq ft per hour = 3.9 hours
Labor Cost: 3.9 hours x $25/hour = $97.50
Total Stucco Cost: $960 (material) + $97.50 (labor) = $1,057.50
Summary of Costs
Component Cost ($)
Primer Application
- Labor Cost $39
- Material Cost $210
Total Primer Cost $249
Stucco Application
- Labor Cost $97.50
- Material Cost $960
Total Stucco Cost $1,057.50
Grand Total Cost $1,306.50